A PRINCE2 project is midway through its delivery stage when the Project Manager realizes that the Business Case has not been reviewed since the project was authorized. The project board is concerned that the project may no longer be viable, but no one has been assigned to check the ongoing justification. Which PRINCE2 principle is being violated?

⚠ Common exam trap

The trap here is assuming that the Business Case only needs to be created once during Starting up a Project and then forgotten.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Continued business justification

The Continued business justification principle demands that a PRINCE2 project has a valid Business Case and that it is reviewed and updated at every stage and at each exception. Because the Business Case has not been reviewed since authorization, the project is running without confirmed justification, which directly violates this principle. The other principles address different aspects of project management.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Defined roles and responsibilities

    Why it's wrong here

    Defined roles and responsibilities means every project has a clear organizational structure with accountable roles. The scenario does not indicate that roles are missing or confused; it states that no one has been assigned to check the Business Case, but that is a symptom of the failure to maintain justification, not a breach of the roles principle itself.

  • ✓

    Continued business justification

    Why this is correct

    This principle requires that a project has a justifiable Business Case and that the justification is reviewed and updated throughout the project, not just at the start. Since the Business Case has not been reviewed since authorization, the project no longer fulfills this principle. The project board must ensure the Business Case remains valid at every stage.

  • ✗

    Manage by exception

    Why it's wrong here

    Manage by exception means the project board sets tolerances and only gets involved if the project deviates beyond them. The scenario does not describe a failure to set or respect tolerances; it describes a failure to review the Business Case. Therefore this principle is not the one being violated here.

  • ✗

    Learn from experience

    Why it's wrong here

    Learn from experience requires seeking lessons from previous projects and throughout the current project. The scenario says nothing about lessons being ignored or not captured. The problem is specifically that the ongoing justification for the project has not been checked, so this principle is not the relevant one.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,189 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PeopleCert exam blueprint

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.