Describe Dynamics 365 Supply Chain ManagementhardMultiple ChoiceObjective-mapped

MB-920 Describe Dynamics 365 Supply Chain Management Practice Question

Contoso, Ltd. is a manufacturer of custom machinery. They use Dynamics 365 Supply Chain Management with production orders and subcontracting. A production order for a custom drilling machine requires a specialized heat treatment process that is performed by an external vendor. The heat treatment is set up as a route operation with a resource of type 'Vendor' and a subcontracting purchase agreement. The production order has been released and started, but the vendor reports that they have not received the purchase order for the heat treatment service. The production planner checks the purchase order and finds that it has not been created yet. The planner confirms that the purchase agreement is active and covers the required service. What is the most likely reason that the purchase order was not automatically generated?

⚠ Common exam trap

Many candidates assume a released production order automatically generates all subcontracting purchase orders, but the system requires the route operation to be scheduled first to trigger the purchase order creation.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The operation for heat treatment has not been scheduled on the production route.

In Dynamics 365 Supply Chain Management, a subcontracting purchase order is automatically generated only after the corresponding route operation has been scheduled on the production route. Without scheduling, the system does not know when the service is needed and therefore does not trigger the purchase order creation, even if the purchase agreement is active and the production order has been released.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The purchase agreement has expired or is not approved.

    Why it's wrong here

    The planner confirmed the purchase agreement is active and covers the service.

  • The operation for heat treatment has not been scheduled on the production route.

    Why this is correct

    The system generates the purchase order only after the operation is scheduled; unscheduled operations do not trigger purchase order creation.

  • The production order status is 'Estimated' and needs to be released first.

    Why it's wrong here

    The order is already released and started, so status is beyond 'Estimated'.

  • The vendor resource is not set up correctly in the system.

    Why it's wrong here

    The resource type 'Vendor' is appropriate for subcontracting; this is not the issue.

About these practice questions

Courseiva writes every MB-920 question from scratch — 930 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This MB-920 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-920 exam.