MB-920 Practice Question: A consulting firm uses Dynamics 365 Project…

A consulting firm uses Dynamics 365 Project Operations to manage fixed-price projects. During project execution, the project manager notices that the actual cost is exceeding the budget. What should the project manager do to track and communicate the impact on profit?

⚠ Common exam trap

Many candidates confuse cost performance metrics (CPI) with schedule metrics (SPI) or operational metrics (resource utilization), leading them to select options that address resource allocation or schedule delays instead of the direct cost-to-profit impact.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Review the Cost Performance Index (CPI) on the project and update the estimate at completion (EAC).

In Dynamics 365 Project Operations, the Cost Performance Index (CPI) is the key metric for measuring cost efficiency on a project. When actual costs exceed the budget, the project manager should review the CPI and update the Estimate at Completion (EAC) to forecast the total expected cost based on current performance, directly communicating the impact on profit.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Analyze resource utilization percentages to identify over-allocated resources.

    Why it's wrong here

    Resource utilization does not directly measure profit impact.

  • Review the Cost Performance Index (CPI) on the project and update the estimate at completion (EAC).

    Why this is correct

    CPI is the correct metric to monitor cost efficiency and forecast final costs.

  • Review the Schedule Performance Index (SPI) to assess if the project is behind schedule.

    Why it's wrong here

    SPI measures schedule, not cost performance.

  • Compare the project budget to the actual cost in the project invoice.

    Why it's wrong here

    Invoices reflect billed amounts, not ongoing cost efficiency.

About these practice questions

Courseiva writes every MB-920 question from scratch — 930 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This MB-920 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-920 exam.