A project manager is tracking remaining work over the course of a sprint to see if the team is on pace to complete all committed stories. Which agile artifact should the project manager use?
A burndown chart plots remaining work against time across the sprint, directly showing whether the team's current pace will reach zero by the sprint's end. This satisfies the stem's requirement to track remaining work and assess whether all committed stories will be completed on schedule.
Why this answer
A burndown chart tracks the amount of remaining work (typically story points or hours) over the sprint duration, showing whether the team is on pace to complete all committed stories by sprint end. It plots remaining work on the Y-axis against time on the X-axis, with an ideal trend line for comparison.
Exam trap
PK0-005 often tests the confusion between burndown (remaining work over time within a sprint) and burnup (completed work over time, often across sprints), or between velocity (cross-sprint throughput) and burndown (intra-sprint pace).
How to eliminate wrong answers
Option A is wrong because a velocity chart shows the amount of work completed per sprint across multiple sprints, used for forecasting capacity, not for tracking intra-sprint progress. Option B is wrong because a burnup chart shows work completed (and sometimes scope changes) over time, but it is less commonly used for daily sprint pace tracking than the burndown. Option D is wrong because a Gantt chart is a waterfall scheduling tool showing task dependencies and timelines, not an agile sprint tracking artifact.