A project manager is tracking remaining work over the course of a sprint to see if the team is on pace to complete all committed stories. Which agile artifact should the project manager use?
Correct – burndown tracks remaining work.
Why this answer
A burndown chart shows remaining work (e.g., story points) over time in a sprint, helping visualize whether the team is on track.