PMP • Practice Exam 51
Free PMP practice exam — 20 questions with explanations. Set 51. No signup required.
A new regulatory requirement has been discovered that will affect your project's deliverables. The requirement is mandatory and must be implemented before the project can close. Your team has the skills to implement it, but it will add two months to the schedule. The sponsor is pushing for the original deadline. What should you do FIRST?