You are the project manager for a large-scale data migration project from on-premises servers to AWS. The project involves migrating 50 terabytes of sensitive customer data. The team has completed the initial assessment and is now in the planning phase. The Chief Information Security Officer (CISO) has mandated that all data must be encrypted in transit and at rest. Additionally, the migration must minimize downtime and ensure data integrity. The project has a tight budget and schedule. During a planning meeting, the lead architect proposes using AWS Snowball Edge devices for the initial bulk transfer, followed by AWS DataSync for ongoing replication. However, the CISO is concerned about encryption key management and audit trails. As the project manager, what should you do first to address the CISO's concerns?