A project manager is managing a construction project and notices that the actual cost for concrete work is consistently 15% above budget. The earned value (EV) is $100,000, and the actual cost (AC) is $115,000. The project manager wants to estimate the cost at completion (EAC) if this trend continues. Which formula should the project manager use?