PMP • Practice Test 30
Free PMP practice test — 15 questions with explanations. Set 30. No signup required.
In your agile project, the team's velocity has been declining over the past three sprints from 30 to 25 to 20 story points. The team members report feeling overworked and demotivated. The daily standup meetings are running long, and the product owner is adding too many stories each sprint. What should the project manager do FIRST?