PMP • Practice Test 26
Free PMP practice test — 15 questions with explanations. Set 26. No signup required.
Your project is using a predictive approach, and you are at the midpoint. The earned value analysis shows: EV = $450,000, PV = $500,000, AC = $550,000. The CPI is 0.82 and SPI is 0.90. The sponsor asks for a forecast of the total cost at completion. What is the best estimate for EAC assuming the current cost performance is typical of future performance?