During a Sprint, a stakeholder frequently interrupts the developers to request minor changes to the current Sprint Backlog items. As a Scrum Master, what is the best course of action?
Trap 1: Allow the changes to keep the stakeholder satisfied.
Accepting ad-hoc changes mid-Sprint creates instability and prevents the team from meeting their commitment. Continuous interruptions diminish throughput and violate the foundational principle of Sprint stability, which is intended to protect the Developers from external influence and ensure the integrity of the work items currently in progress.
Trap 2: Facilitate a discussion with the team and stakeholder regarding the…
This approach addresses the root cause by fostering transparency and understanding. By surfacing the impact on the Sprint Goal, the Scrum Master helps stakeholders recognize the cost of context switching. This collaborative problem-solving approach empowers the team to set boundaries while maintaining a positive relationship with the stakeholder group.
Trap 3: Ask the Developers to ignore the stakeholder.
Ignoring a stakeholder is unprofessional and damages organizational relationships. Scrum promotes transparency and collaboration, not isolation. The Scrum Master should act as a bridge between the team and stakeholders, providing coaching to ensure that communication channels are effective without disrupting the team's focus on the Sprint Goal.
- A
Allow the changes to keep the stakeholder satisfied.
Why it fails: Accepting ad-hoc changes mid-Sprint creates instability and prevents the team from meeting their commitment. Continuous interruptions diminish throughput and violate the foundational principle of Sprint stability, which is intended to protect the Developers from external influence and ensure the integrity of the work items currently in progress.
- B
Redirect the stakeholder to the Product Owner.
While the Product Owner is responsible for the Product Backlog, simply redirecting does not address the underlying issue of team protection. The Scrum Master must actively facilitate a conversation about how these interruptions affect the team's ability to achieve the Sprint Goal and define boundaries for stakeholder interactions.
- C
Facilitate a discussion with the team and stakeholder regarding the impact of these interruptions.
Why it fails: This approach addresses the root cause by fostering transparency and understanding. By surfacing the impact on the Sprint Goal, the Scrum Master helps stakeholders recognize the cost of context switching. This collaborative problem-solving approach empowers the team to set boundaries while maintaining a positive relationship with the stakeholder group.
- D
Ask the Developers to ignore the stakeholder.
Why it fails: Ignoring a stakeholder is unprofessional and damages organizational relationships. Scrum promotes transparency and collaboration, not isolation. The Scrum Master should act as a bridge between the team and stakeholders, providing coaching to ensure that communication channels are effective without disrupting the team's focus on the Sprint Goal.