A Scrum Master at a logistics company learns that the procurement department signs multi-year contracts with a single vendor for all software testing tools, and that this vendor's platform cannot support automated regression suites. Scrum Teams are manually regression-testing for several days each Sprint, and the Definition of Done is eroding. What is the most appropriate action for the Scrum Master to serve the organization?

⚠ Common exam trap

The trap here is treating a procurement or vendor constraint as permanently outside the Scrum Master's influence, when serving the organization means surfacing systemic impediments and coaching the people who can change them.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Work with the procurement department and teams to make the testing-tool limitation and its impact on delivery visible, and coach them on options such as adding automation-capable tooling or amending the vendor agreement to support the Definition of Done.

The Scrum Master serves the organization by helping it see how structural decisions, including procurement contracts, affect the teams' ability to produce a Done Increment. Making the tooling limitation and its delivery impact visible, then coaching procurement and teams toward options like automation-capable tools or amended agreements, addresses the root cause. This preserves the Definition of Done and enables empiricism rather than masking the problem with weaker standards.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Record the manual regression time as an impediment in the Sprint Retrospective and continue with the current vendor until the contract expires, because procurement decisions are outside the Scrum Master's scope and cannot be influenced.

    Why it's wrong here

    Logging the impediment without acting leaves the organization unaware of a systemic constraint that undermines every team using the contract. The claim that procurement cannot be influenced is false; the Scrum Master serves the organization by coaching across departments. Waiting years for a contract to expire allows the Definition of Done to keep eroding and normalizes lower quality, which is contrary to the role's purpose.

  • ✗

    Advise the teams to reduce the scope of their Definition of Done so that manual regression testing no longer blocks a Product Increment, allowing them to meet Sprint Goals with the current tooling.

    Why it's wrong here

    Lowering the Definition of Done to fit a tooling constraint hides the problem and degrades quality. The Scrum Master serves the organization by addressing the impediment, not by weakening the quality standard. Reducing the Definition of Done may make Sprints appear successful, but it increases technical risk and contradicts the empirical transparency Scrum depends on. The procurement constraint is the real issue and should be raised with the people who can change it.

  • ✓

    Work with the procurement department and teams to make the testing-tool limitation and its impact on delivery visible, and coach them on options such as adding automation-capable tooling or amending the vendor agreement to support the Definition of Done.

    Why this is correct

    This is correct because serving the organization means helping it understand how procurement decisions affect the teams' ability to deliver a Done Increment. By making the impact visible and coaching procurement and teams together, the Scrum Master enables a systemic fix rather than a workaround. This respects the organization's contracting reality while advocating for the technical capability the Definition of Done requires.

  • ✗

    Direct the developers to build a custom automation framework from scratch during Sprint time, since the Scrum Master is responsible for removing impediments and can assign technical work when tooling is inadequate.

    Why it's wrong here

    The Scrum Master does not assign technical work or dictate engineering solutions; that authority belongs to the self-managing developers. Ordering a from-scratch framework also ignores the procurement constraint that caused the problem and may create unsustainable maintenance work. While removing impediments is part of the role, it is done by coaching and facilitating organizational change, not by directing the team's technical choices.

About these practice questions

This CSM question is part of Courseiva's 312-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scrum Alliance exam blueprint

This CSM practice question is part of Courseiva's free Scrum Alliance certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CSM exam.