POPM Leadership for PI Planning Practice Question
You are a Business Owner for an Agile Release Train. During the PI Planning event, a team presents a draft plan that includes several stretch objectives. The team's Product Owner explains that the stretch objectives represent work the team hopes to complete if capacity allows. As a Business Owner, what should you do during the draft plan review?
⚠ Common exam trap
The trap here is conflating stretch objectives with committed objectives, leading to a demand that teams commit to aspirational work or remove it entirely rather than treating it as optional.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Review the committed objectives for business value and alignment with the train's goals, and acknowledge the stretch objectives as optional work that does not affect the commitment.
Business Owners validate that committed objectives align with business strategy and deliver value, while stretch objectives remain optional. The correct action is to evaluate the committed objectives and acknowledge the stretch work without requiring it to be committed. This respects the team's planning autonomy, preserves realistic capacity assumptions, and keeps the confidence vote meaningful. It also reinforces the SAFe distinction between committed and stretch objectives.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Review the committed objectives for business value and alignment with the train's goals, and acknowledge the stretch objectives as optional work that does not affect the commitment.
Why this is correct
This action correctly distinguishes between committed and stretch objectives. Business Owners are responsible for validating that committed objectives deliver the intended business outcomes and align with the portfolio strategy, while stretch objectives remain optional. Acknowledging them without demanding commitment preserves the team's ability to plan realistically and maintains the integrity of the confidence vote.
- ✗
Ask the team to remove the stretch objectives and replace them with additional committed objectives that fill the team's full capacity.
Why it's wrong here
Replacing stretch objectives with additional commitments assumes teams should plan to 100 percent of theoretical capacity, which ignores variability, unplanned work, and the need for slack. It also removes the team's ability to signal aspirational work transparently. Business Owners should support sustainable planning, not maximize committed scope at the expense of predictability and quality.
- ✗
Accept the plan but ask the team to convert all stretch objectives into committed objectives so that the train can count on the additional scope.
Why it's wrong here
Converting stretch objectives into commitments defeats their purpose. Stretch objectives are intentionally non-committed so teams can pursue them only if capacity permits, without jeopardizing the committed plan. Forcing them into commitments inflates demand and risks overcommitment. Business Owners should respect the distinction and focus on the value and confidence of the committed objectives.
- ✗
Reject the plan because stretch objectives are not allowed in a PI plan and must be removed before the final review.
Why it's wrong here
Stretch objectives are a legitimate and encouraged part of PI planning. They allow teams to signal aspirational work without committing to it, which helps manage variability. Rejecting the plan outright misapplies SAFe guidance and discourages teams from being transparent about their capacity assumptions. Business Owners should instead assess whether the committed objectives are realistic and valuable.
About these practice questions
Courseiva writes every POPM question from scratch — 336 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint
This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.