What is the main goal of the Management Review and Problem Solving session during PI Planning?

⚠ Common exam trap

Candidates often assume the goal is to force teams to complete the original plan. They ignore that the session is specifically designed to adjust scope, resources, and dependencies to ensure achievability.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

To adjust the program scope, people, and resources to ensure the PI plan is achievable.

This session is where leadership addresses the issues that arose during the first day of planning. By reviewing the draft plans and resolving dependencies, scope, and resource constraints, leadership ensures that the final day of planning is productive. This is the critical moment where roadblocks are removed so that teams can finalize a realistic plan that they can confidently commit to during the final session.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    To finalize the release dates for the next three years of the product roadmap.

    Why it's wrong here

    PI Planning focuses on the upcoming Program Increment, not long-term roadmap planning. Three-year planning is too far out for the level of detail required in PI Planning, and attempting to force such long-term commitments would lead to inaccurate and unreliable plans that cannot be sustained.

  • ✓

    To adjust the program scope, people, and resources to ensure the PI plan is achievable.

    Why this is correct

    The session allows leaders to make the necessary structural adjustments to ensure success. By addressing capacity and resource gaps or refining scope, leadership ensures the plan is realistic, which is essential for maintaining the commitment and morale of the teams who will execute the work.

  • ✗

    To celebrate the team's progress and distribute rewards for the previous PI's performance.

    Why it's wrong here

    While celebrating is important, it is not the primary purpose of this session. This time is strictly reserved for solving the critical problems that currently impede the planning process. Using this time for non-essential activities would jeopardize the ability to complete a viable plan for the upcoming PI.

  • ✗

    To conduct the confidence vote for all teams on the Agile Release Train.

    Why it's wrong here

    The confidence vote happens at the end of the second day of PI Planning, not during the Management Review session. This session is for leadership to prepare the ground for that vote by solving the problems that would otherwise prevent a high-confidence outcome.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

Courseiva writes every POPM question from scratch — 336 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.