PI Execution →mediumMultiple Select

POPM PI Execution Practice Question

During PI Execution, the Product Manager observes that the ART is not fully aligned on the value of a new feature that was added mid-PI to address a competitive threat. Which TWO actions should the Product Manager take to ensure effective PI execution? (Choose two.)

⚠ Common exam trap

The trap here is assuming that a mid-PI addition requires an emergency replanning session or top-down mandate, rather than using standard backlog refinement and communication channels.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Update the program backlog and collaborate with the Product Owners to refine and prioritize the feature across team backlogs.

The Product Manager should update the program backlog and work with Product Owners to refine and prioritize the feature, ensuring it flows into team backlogs. Additionally, communicating the strategic rationale at the System Demo builds alignment and gathers feedback. These actions address both the logistical and motivational aspects of the misalignment, enabling effective PI execution.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Ask the Business Owners to mandate the feature's inclusion in all team backlogs without further discussion.

    Why it's wrong here

    Mandating inclusion without discussion undermines team empowerment and may not address the underlying misalignment. The Product Manager should facilitate understanding and buy-in, not rely on top-down mandates. Teams need to understand the 'why' to effectively deliver the feature.

  • ✓

    Update the program backlog and collaborate with the Product Owners to refine and prioritize the feature across team backlogs.

    Why this is correct

    The Product Manager owns the program backlog and must ensure the new feature is properly refined and prioritized. Collaborating with Product Owners ensures alignment and smooth flow into team backlogs. This action directly addresses the misalignment by making the feature's value and requirements clear to all teams.

  • ✗

    Request the Release Train Engineer to call an emergency PI Planning session to replan the entire PI.

    Why it's wrong here

    An emergency PI Planning session is excessive for a single feature addition. PI Planning is a significant event that occurs at the start of a PI; mid-PI replanning is typically handled through backlog refinement and coordination. Calling for a full replan would waste time and resources.

  • ✓

    Communicate the strategic rationale for the feature at the next System Demo and solicit feedback from stakeholders.

    Why this is correct

    The System Demo is a key event for aligning stakeholders and teams on solution value. By communicating the strategic rationale, the Product Manager can build shared understanding and gather feedback that may influence the feature's direction. This fosters transparency and helps the ART see the bigger picture.

  • ✗

    Direct the teams to immediately stop current work and swarm on the new feature to accelerate delivery.

    Why it's wrong here

    Unilaterally redirecting teams to swarm on a new feature disrupts planned work and can cause chaos. The Product Manager should not bypass normal prioritization and team autonomy. Swarming might be appropriate later if the feature becomes critical, but it is not the first step to create alignment.

About these practice questions

This POPM question is part of Courseiva's 336-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.