PI Execution →hardMultiple Choice

POPM PI Execution Practice Question

During PI Execution, a Product Manager notices that two teams are frequently blocked by a shared component that is owned by a third team with limited capacity. The blocks are causing delays in delivering features. What is the most effective action for the Product Manager to take?

⚠ Common exam trap

The trap here is opting for a quick fix like escalation or workarounds instead of facilitating a systemic solution that involves the affected teams.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Facilitate a discussion with the affected teams and the third team to explore options such as capacity allocation, component ownership changes, or enabler work.

The most effective action is to facilitate a discussion among the teams to find a collaborative solution, such as allocating capacity for the shared component, changing ownership, or investing in enablers. This addresses the bottleneck sustainably and aligns with the Product Manager's role in optimizing flow across the ART.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Facilitate a discussion with the affected teams and the third team to explore options such as capacity allocation, component ownership changes, or enabler work.

    Why this is correct

    This approach addresses the root cause by bringing together stakeholders to find a sustainable solution. Options might include dedicating capacity for shared component work, redistributing ownership, or investing in enablers to improve the component. The Product Manager's role is to facilitate alignment and remove impediments at the ART level.

  • ✗

    Advise the affected teams to work around the shared component by building their own temporary solutions.

    Why it's wrong here

    Building temporary solutions increases technical debt and duplication, and may not be feasible. It also undermines the ART's goal of integrated solutions. The Product Manager should promote collaboration and systemic fixes, not workarounds that can create long-term issues.

  • ✗

    Instruct the third team to stop all other work and prioritize the shared component requests immediately.

    Why it's wrong here

    While urgent, stopping all other work could disrupt the third team's own PI Objectives and create new delays. The Product Manager should facilitate a collaborative solution that balances priorities across teams, rather than issuing unilateral directives that may cause further bottlenecks.

  • ✗

    Escalate the issue to the Release Train Engineer and request that they reassign the shared component to another team.

    Why it's wrong here

    Escalation may be necessary, but the Product Manager should first attempt to resolve the issue collaboratively. Reassigning ownership without understanding the implications could cause more problems. The RTE can help, but the Product Manager is better positioned to facilitate cross-team prioritization and capacity planning.

About these practice questions

One of 336 original POPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.