Which TWO roles are primarily responsible for ensuring the program roadmap is successfully executed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

The program manager and project managers are responsible for managing the delivery against the roadmap.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why this is correct

    Executes the work outlined in the roadmap at the component level.

  • Database Administrator

    Why it's wrong here

    A technical support role, not a management role for the roadmap.

  • Facilities Manager

    Why it's wrong here

    Unrelated to the program execution.

  • Program Manager

    Why this is correct

    Directly responsible for the roadmap's success.

  • External Auditor

    Why it's wrong here

    Auditors evaluate performance, they do not execute it.

About these practice questions

Courseiva writes every PgMP question from scratch — 197 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.