PgMP Strategic Program Alignment Practice Question
Which TWO roles are primarily responsible for ensuring the program roadmap is successfully executed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project Manager
The program manager and project managers are responsible for managing the delivery against the roadmap.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project Manager
Why this is correct
Executes the work outlined in the roadmap at the component level.
- ✗
Database Administrator
Why it's wrong here
A technical support role, not a management role for the roadmap.
- ✗
Facilities Manager
Why it's wrong here
Unrelated to the program execution.
- ✓
Program Manager
Why this is correct
Directly responsible for the roadmap's success.
- ✗
External Auditor
Why it's wrong here
Auditors evaluate performance, they do not execute it.
About these practice questions
Courseiva writes every PgMP question from scratch — 197 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.