PgMP Program Life Cycle Management Practice Question
Which document is created during the Program Formulation phase to establish the program's strategic business value?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Program Charter
The program charter, developed during formulation, formally authorizes the program and outlines its strategic business case.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Program Management Plan
Why it's wrong here
This is developed in the planning phase.
- ✓
Program Charter
Why this is correct
The charter establishes the mandate and strategic alignment.
- ✗
Program Roadmap
Why it's wrong here
The roadmap is a planning document reflecting timelines and milestones.
- ✗
Benefits Realization Plan
Why it's wrong here
This is a detailed planning document.
About these practice questions
This PgMP question is part of Courseiva's 197-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.