Which document is created during the Program Formulation phase to establish the program's strategic business value?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Program Charter

The program charter, developed during formulation, formally authorizes the program and outlines its strategic business case.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Program Management Plan

    Why it's wrong here

    This is developed in the planning phase.

  • Program Charter

    Why this is correct

    The charter establishes the mandate and strategic alignment.

  • Program Roadmap

    Why it's wrong here

    The roadmap is a planning document reflecting timelines and milestones.

  • Benefits Realization Plan

    Why it's wrong here

    This is a detailed planning document.

About these practice questions

This PgMP question is part of Courseiva's 197-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.