Courseiva
Program Life Cycle ManagementmediumMultiple ChoiceObjective-mapped

PgMP Program Life Cycle Management Practice Question

How do you manage risks that are common to multiple projects within a program?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Manage them at the program level as shared risks.

Common risks should be managed at the program level to ensure a consistent approach and resource allocation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Assign them to the most senior project manager.

    Why it's wrong here

    This is not a governance best practice.

  • Ignore them until they impact a project.

    Why it's wrong here

    This is reactive, not proactive.

  • Manage them at the program level as shared risks.

    Why this is correct

    Managing shared risks centrally is a core program management competency.

  • Manage them individually in each project.

    Why it's wrong here

    This is inefficient and loses the program-level benefit of shared risk management.

About these practice questions

Courseiva writes every PgMP question from scratch — 197 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PgMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PgMP exam.