PfMP Portfolio Performance Management Practice Question
Which document is updated when a project is closed within a portfolio?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Portfolio Roadmap.
The Portfolio Roadmap and the Component Inventory must be updated to reflect the status change.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The Portfolio Roadmap.
Why this is correct
The roadmap must show that the component is no longer active.
- ✗
The Project Charter.
Why it's wrong here
The project charter is not a portfolio-level document.
- ✗
The Corporate Strategic Plan.
Why it's wrong here
Corporate strategy is not changed by individual project closures.
- ✗
The Human Resources handbook.
Why it's wrong here
This is not related to portfolio status.
About these practice questions
This PfMP question is part of Courseiva's 199-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PfMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PfMP exam.