A company uses a Power Platform environment that contains several production apps. They need to ensure that changes to these apps are reviewed and approved before deployment to the production environment. What should they implement?
⚠ Common exam trap
Many candidates confuse data governance (DLP) or auditing (Purview) with the deployment approval process, or mistakenly think that granting admin rights to all developers is a valid way to manage changes, rather than recognizing the need for a formal ALM pipeline with approval gates.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Use managed solutions and Azure DevOps for application lifecycle management (ALM) with deployment gates.
Managed solutions and Azure DevOps with deployment gates provide a structured Application Lifecycle Management (ALM) process. This allows changes to be reviewed, tested, and approved before deployment to a production environment, ensuring governance and control over modifications.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Create data loss prevention (DLP) policies for the production environment.
Why it's wrong here
DLP policies restrict which connectors and actions apps may use, governing data movement rather than gating deployment of changes into production. It is tempting because DLP is the primary Power Platform governance control, and it would be correct where the requirement is preventing apps from accessing unauthorised data sources.
- ✓
Use managed solutions and Azure DevOps for application lifecycle management (ALM) with deployment gates.
Why this is correct
Managed solutions are immutable in the target environment, so production changes cannot be edited directly. Pairing them with Azure DevOps pipelines enforces deployment gates, requiring review and approval before release. This satisfies the requirement that changes be approved prior to production deployment.
- ✗
Assign the System Administrator role to all developers.
Why it's wrong here
System Administrator grants full configuration rights, including direct deployment to production, removing any review gate rather than creating one. It is tempting because broad privileges feel like control over who can change apps, and it would be correct where developers need unrestricted build and environment-management capability.
- ✗
Configure Microsoft Purview to audit changes and require approval.
Why it's wrong here
Microsoft Purview audits and retains records of activity; it does not intercept deployments or enforce an approval step before changes reach production. It is tempting because auditing sounds like governance over changes, and it would be correct where the requirement is compliance evidence and investigation rather than pre-deployment authorisation.
Go deeper
Related to this question
About these practice questions
This PL-900 question is part of Courseiva's 701-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PL-900 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PL-900 exam.