hardMultiple ChoiceObjective-mapped
MB-920 Practice Question: Implementing Dynamics 365 Project Operations and…
A company is implementing Dynamics 365 Project Operations and wants to ensure that project costs are accurately tracked for both time and materials (T&M) and fixed-price contracts. The company uses a single project for both types of contracts. Which approach should be used to correctly invoice each contract type?
⚠ Common exam trap
A common mix-up: candidates assume a single project must have a single billing method, but Dynamics 365 Project Operations supports multiple contracts per project, each with its own billing method, enabling accurate hybrid invoicing.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Create two project contracts, one T&M and one fixed-price, and link both to the same project.
Dynamics 365 Project Operations allows multiple project contracts to be linked to a single project, enabling different billing methods (T&M and fixed-price) for the same project. This ensures that time and material costs are tracked and invoiced according to the T&M contract terms, while fixed-price milestones are invoiced under the fixed-price contract, all from the same project data.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Create two project contracts, one T&M and one fixed-price, and link both to the same project.
Why this is correct
Multiple contracts can be linked to one project, each with its own billing method.
- ✗
Create two separate projects and link each to its own contract.
Why it's wrong here
Separate projects would not share resources and schedules.
- ✗
Create a single project contract with the billing method set to fixed-price and adjust invoices manually.
Why it's wrong here
Manual adjustments are not recommended.
- ✗
Create one project contract with a billing method of T&M and manually create invoices for the fixed-price portion.
Why it's wrong here
A contract has a single billing method.
Go deeper
Related to this question
About these practice questions
Courseiva writes every MB-920 question from scratch — 930 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This MB-920 practice question is part of Courseiva's free Microsoft certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the MB-920 exam.