Courseiva
Information Security Risk ManagementhardMultiple SelectObjective-mapped

CISM High residual risk actions Practice Question

An organization has a high residual risk after implementing all feasible controls. According to CISM best practices, which of the following should the information security manager do? (Select TWO.)

⚠ Common exam trap

Candidates often confuse 'documenting and accepting' (Option B) as sufficient, overlooking the CISM requirement that risk acceptance must be formally escalated to and approved by senior management, not just recorded by the security manager.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Escalate to senior management for risk acceptance

When residual risk remains high after all feasible controls are implemented, the information security manager should escalate the risk to senior management for formal risk acceptance (Option A). This aligns with CISM best practices, as senior management holds the authority to accept risks that exceed the organization's risk appetite. Additionally, implementing compensating controls (Option C) can further reduce residual risk to an acceptable level, even if primary controls are already in place.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Document the risk in the risk register and accept it

    Why it's wrong here

    Documentation alone is not sufficient; escalation is needed for high residual risk.

  • Immediately perform a new risk assessment

    Why it's wrong here

    A new assessment may be done later, but the immediate action is to escalate and consider additional controls.

Option-by-option analysis

Why each answer is right or wrong

Understanding why wrong answers are wrong — and when they would be correct — is what separates a 750 score from a 900. The CISM exam frequently reuses these exact scenarios with slightly different constraints.

Escalate to senior management for risk acceptanceCorrect answer
Document the risk in the risk register and accept itWrong answer — click to see why

Why this is wrong here

Documentation alone is not sufficient; escalation is needed for high residual risk.

Immediately perform a new risk assessmentWrong answer — click to see why

Why this is wrong here

A new assessment may be done later, but the immediate action is to escalate and consider additional controls.

Analysis generated from the official CISMblueprint and verified against question context. The “when correct” sections are what AI assistants cite when candidates ask “what’s the difference between these options?”

About these practice questions

One of 871 original CISM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CISM practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CISM exam.