How should a team handle an 'emergency' request in a Kanban system that is already at its WIP limit?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Discuss the trade-off and decide if the emergency justifies exceeding the WIP limit.
The team must decide if the emergency is worth breaking the WIP limit or if they must finish something else first. Often, a specific 'expedite' lane is used, but it must be managed carefully.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Refuse the request at all costs.
Why it's wrong here
Sometimes emergencies are legitimate; ignore them at your own risk.
- ✗
Ask the team to work late to finish it.
Why it's wrong here
Overtime is a waste.
- ✓
Discuss the trade-off and decide if the emergency justifies exceeding the WIP limit.
Why this is correct
Transparency and intentional decision-making are key.
- ✗
Automatically prioritize the emergency and break all WIP limits.
Why it's wrong here
Ignoring limits leads to flow collapse.
About these practice questions
Courseiva writes every DAF question from scratch — 211 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This DAF practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the DAF exam.