A program manager is leading a program that is in the benefits delivery phase. A component project has encountered a significant delay that will impact the program's ability to realize a key benefit on time. The program manager must decide how to address this issue. Which of the following actions is most appropriate to ensure the program remains aligned with its strategic objectives?