Supporting ART Events practice questions

This domain covers how a SAFe Scrum Master supports Agile Release Train events: PI Planning, System Demo, Inspect and Adapt, and Coach Sync. Questions place you in a scenario, then ask what the Scrum Master facilitates or escalates next, testing whether you enable ART-level flow rather than manage a single team.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Editorial oversight:Johnson Ajibi· MSc IT Security, IEEE Senior Member
20 questionsDomain: Supporting ART Events

What the exam tests

What to know about Supporting ART Events

You must be able to facilitate ART events so the train inspects a real integrated increment and improves. The single most important thing: keep the System Demo and Inspect and Adapt focused on the working solution and root causes, not polished slides or status reporting.

Facilitating the Inspect and Adapt Problem-Solving Workshop after metrics review

Coaching teams toward one shared Definition of Done for ART integration

Ensuring System Demo shows the integrated solution, not slide decks

Surfacing cross-team dependencies and impediments during Coach Sync

Watch out for

Common Supporting ART Events exam traps

  • ▸Treating the Problem-Solving Workshop as a status meeting instead of facilitating root-cause analysis and owned improvement actions
  • ▸Letting each team keep its own Definition of Done, which breaks integration at the System Demo
  • ▸Solving another team's problem yourself during Coach Sync rather than coaching and escalating to the RTE

Practice set

Supporting ART Events questions

20 questions · select your answer, then reveal the explanation

Which preparation activity is essential for a successful PI Planning event according to the Scrum Master's responsibilities?

What are TWO primary outputs of the PI Planning event? (Choose two.)

When a team identifies a risk during PI Planning, which TWO categories are part of the ROAM technique? (Choose two.)

Which THREE components make up the Inspect and Adapt event? (Choose THREE)

Refer to the exhibit. During the Scrum of Scrums at PI Planning, the Scrum Master for Team B notices the dependency link. How should the Scrum Master address this?

Exhibit

{
  "Program_Board": {
    "Iteration_1.1": {"Team_A": "Dependency_X (Red)"},
    "Iteration_1.2": {"Team_B": "Feature_Beta (Blue)"},
    "Dependency_Link": "Feature_Beta -> Dependency_X"
  }
}

During the Draft Plan Review in PI Planning, what THREE pieces of information are teams expected to present? (Choose THREE)

Which TWO metrics are typically reviewed during the Quantitative and Qualitative Measurement part of the Inspect and Adapt event? (Choose TWO)

Refer to the exhibit. Based on the PI Objectives and their Business Value (BV) scores, what should the Scrum Master highlight during the Inspect and Adapt Quantitative Measurement phase?

Exhibit

[
  {"Objective": "Cloud Migration", "Planned_BV": 10, "Actual_BV": 10},
  {"Objective": "API Security", "Planned_BV": 8, "Actual_BV": 0},
  {"Objective": "(Uncommitted) Legacy Cleanup", "Planned_BV": 5, "Actual_BV": 5}
]

During the first iteration execution of a Program Increment, the Scrum Master notices that the Agile Release Train's teams are struggling to integrate their work continuously. Feature dependencies are discovered late, threatening the PI commitment. What is the most effective action for the Scrum Master to take?

Which TWO actions are primary responsibilities of the Scrum Master during the Scrum of Scrums (SoS) event?

Refer to the exhibit. As a Scrum Master for Team Alpha, what is the most appropriate action to take at the next Scrum of Scrums based on the JSON data?

Exhibit

{
  "program_board": {
    "feature_id": "F-102",
    "dependency": {
      "from_team": "Team_Alpha",
      "to_team": "Team_Beta",
      "iteration": 3,
      "status": "delayed"
    },
    "feature_delivery": "Iteration 3"
  }
}

During the Scrum of Scrums (SoS) meeting, a Scrum Master from Team Beta reports that they will not meet a dependency needed by Team Alpha for an upcoming feature. The Scrum Master for Team Alpha is present. What is the most appropriate action for Team Alpha's Scrum Master to take next?

During the ART Sync, the Scrum Master for Team Delta hears Team Echo report that they will not finish a shared API feature because Team Delta has not yet delivered the authentication service. Team Delta's board shows the authentication service is in progress but not yet started. What should the Scrum Master for Team Delta do first?

During the first day of PI Planning, the team realizes their drafted plan requires dependencies from another Agile Release Train (ART) that have not been committed. What is the most appropriate action for the Scrum Master to facilitate?

Which Agile Release Train event provides the primary mechanism for synchronizing the work of all Agile Teams on the train?

During the first day of PI Planning, a team realizes that a critical architectural dependency will prevent them from completing their committed features. How should the Scrum Master coach the team for the Management Review and Problem-Solving session?

A Scrum Master notices that the System Demo is frequently delayed because teams are struggling to integrate their code at the end of the iteration. What is the best way to support this ART event?

Which TWO activities occur during the ART Sync event to ensure the train stays on track? (Choose two.)

During the Problem-Solving Workshop of the Inspect and Adapt event, several teams identify 'lack of automated testing' as a root cause. What is the Scrum Master's role in the next step?

During Team Breakout #1 in PI Planning, the team finds that their capacity is exceeded by the features assigned to them. What should the Scrum Master do first?

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Supporting ART Events sessions

Start a Supporting ART Events only practice session

Every question in these sessions is drawn from the Supporting ART Events domain — nothing else.

Related practice questions

Related SSM topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the SSM exam test about Supporting ART Events?
You must be able to facilitate ART events so the train inspects a real integrated increment and improves. The single most important thing: keep the System Demo and Inspect and Adapt focused on the working solution and root causes, not polished slides or status reporting.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Supporting ART Events questions in a focused session?
Yes — the session launcher on this page draws every question from the Supporting ART Events domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other SSM topics?
Use the topic links above to move to related areas, or go back to the SSM question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the SSM exam covers. They are not copied from any real exam or dump site.