Refer to the Exhibit Practice Questions

Practise SAFe Scrum Master practice questions — original exam-style scenarios covering every exam domain, with detailed explanations, wrong-answer analysis, and common exam traps.

11
scenario questions
SSM
exam code
Scaled Agile
vendor

Scenario guide

How to approach refer to the exhibit practice questions

Practise exhibit-style questions that ask you to read a topology, table, command output or diagram before choosing the best answer.

Quick answer

Exhibit-style questions test whether you can read a topology, command output, diagram or table before choosing the best answer.

How to extract the relevant detail from an exhibit.

How topology, command output or routing information affects the answer.

How to avoid answering from memory before reading the evidence.

How to map the exhibit back to the exam objective.

Related practice questions

Related SSM topic practice pages

Scenario questions usually connect to one or more exam topics. Use these links to review the underlying concepts behind the scenario.

Practice set

Practice scenarios

Question 1mediummultiple choice
Full question →

Refer to the exhibit. As a Scrum Master attending the ART Sync, what is the most appropriate action to take regarding DEP-102?

Exhibit

{
  "ART_Sync_Board": {
    "Dependency_ID": "DEP-102",
    "Description": "Database Schema Update",
    "Provider": "Team-Alpha",
    "Consumer": "Team-Beta",
    "Needed_By": "Iteration 1.3",
    "Status": "Blocked: Hardware Delay"
  }
}
Question 2hardmultiple choice
Full question →

Refer to the exhibit. Why would the Scrum Master coach the team to mark the 'Auth API' objective as uncommitted?

Exhibit

{
  "Team_Objectives": {
    "Committed": ["Objective_1", "Objective_2"],
    "Uncommitted": ["Objective_3 (Auth_API)"],
    "Context": "High_Dependency_on_External_Team"
  }
}
Question 3hardmultiple choice
Full question →

Refer to the exhibit. As the Scrum Master during the middle of the iteration, how should you coach the team regarding their commitment?

Exhibit

Iteration Plan:
- User Story A: 8 pts (Dev complete)
- User Story B: 5 pts (In progress)
- User Story C: 3 pts (Not started)
- Team Velocity: 10 pts
Question 4mediummultiple choice
Full question →

Refer to the exhibit. As a Scrum Master, how should you address the situation described in the log?

Exhibit

LOG_ENTRY: [ERROR] Iteration 3 completed with 45 points; Iteration 4 started with 60 points of planned capacity. [WARN] Team velocity averages 42 points. [INFO] Iteration 4 planning reflects high inter-team dependency on Team B.
Question 5mediummultiple choice
Full question →

Refer to the exhibit. If the team consistently exceeds the 'timebox_max_hours' during planning, what is the Scrum Master's best next step?

Exhibit

JSON Configuration: {'iteration_planning': {'enabled': true, 'timebox_max_hours': 4}, 'retrospective': {'enabled': true, 'max_participants': 'all_team_members'}, 'daily_standup': {'max_minutes': 15}}
Question 6hardmultiple choice
Full question →

Refer to the exhibit. Given these findings, which action should the Scrum Master prioritize to improve team flow?

Exhibit

Iteration Retrospective Input: 1. Developers feeling overwhelmed by mid-iteration requests. 2. Testing is consistently delayed. 3. Daily stand-ups are taking over 25 minutes.
Question 7hardmultiple choice
Full question →

Refer to the exhibit. During PI Planning, leadership encounters a major cross-team dependency blockage that threatens program objectives. When does the Management Review and Problem Solving meeting take place to address this?

Exhibit

{
  "event": "PI Planning",
  "step": "Management Review and Problem Solving",
  "identified_impediment": "Cross-team dependency blockage",
  "participants": ["Release Train Engineer", "Product Management", "System Architect", "Business Owners"]
}
Question 8hardmultiple choice
Full question →

Refer to the exhibit. As the Scrum Master for Blue-Squad, which action should you prioritize during the next Team Sync based on the current JSON status report?

Exhibit

{
  "iteration": "3",
  "team_name": "Blue-Squad",
  "wip_limit": 4,
  "active_items": 7,
  "blocked_items": 2,
  "cycle_time_avg": "11 days"
}
Question 9mediummultiple choice
Full question →

Refer to the exhibit. Given the velocity fluctuations, what is the best topic for the team's next Retrospective?

Exhibit

Team Velocity Trend: Iteration 1: 30, Iteration 2: 32, Iteration 3: 25, Iteration 4: 28.
Question 10mediummultiple choice
Full question →

Refer to the exhibit. Based on the performance report, what should the Scrum Master prioritize to improve the team's effectiveness?

Exhibit

Team Performance Report:
- Velocity Trend: Stable
- Iteration Goals Met: 60%
- Impediment Resolution Time: High
- Scrum Master Focus: Administrative Documentation
Question 11mediummultiple choice
Full question →

Refer to the exhibit. What observation should the Scrum Master share with the team during the next Retrospective?

Exhibit

Team Velocity Log:
- Iteration 1: 20 pts
- Iteration 2: 22 pts
- Iteration 3: 21 pts
- Iteration 4: 18 pts (Scope added mid-iteration)
- Iteration 5: 23 pts