SSM Supporting ART Events Practice Question
During the Inspect and Adapt (I&A) event, the ART's metrics show that the Program Predictability Measure for the last PI was 60%. The RTE facilitates a problem-solving workshop where teams identify 'unclear acceptance criteria' as a root cause. As the Scrum Master for one of the teams, what is your most appropriate next step to support the ART's improvement?
⚠ Common exam trap
The trap here is focusing on a single team's local fix instead of recognizing that the Inspect and Adapt event drives ART-level improvements that should be captured in the ART backlog.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Work with the RTE and other Scrum Masters to create an improvement story for the ART's backlog that addresses acceptance criteria clarity across teams.
The Inspect and Adapt event culminates in the problem-solving workshop, where root causes are identified and improvement items are added to the ART backlog. When a root cause is systemic, the Scrum Master should collaborate with the RTE and other Scrum Masters to create an ART-level improvement story, ensuring a coordinated and tracked solution rather than isolated team fixes.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Work with the RTE and other Scrum Masters to create an improvement story for the ART's backlog that addresses acceptance criteria clarity across teams.
Why this is correct
The Inspect and Adapt event concludes with identifying improvement items that are added to the ART backlog. Since the root cause affects the entire ART, the Scrum Master should collaborate with the RTE and peers to create a systemic improvement story. This ensures the fix is coordinated and tracked, rather than leaving each team to solve it in isolation, which aligns with the event's purpose of driving ART-level improvements.
- ✗
Schedule a separate meeting with your team's Product Owner to rewrite all user stories with clearer acceptance criteria for the next PI.
Why it's wrong here
This action focuses only on one team and does not leverage the ART-level improvement process established by the Inspect and Adapt event. The root cause was identified during a collaborative workshop, and addressing it should involve the broader ART. A team-specific meeting may help locally but misses the opportunity to create a systemic solution that benefits all teams.
- ✗
Update the team's Definition of Done to include a mandatory review of acceptance criteria by the Product Owner before sprint planning.
Why it's wrong here
While improving acceptance criteria is valuable, the problem-solving workshop is an ART-level event, and the root cause may affect multiple teams. Making a unilateral change to one team's Definition of Done does not address the systemic issue across the ART. The Scrum Master should first participate in the ART-level improvement planning to ensure a coordinated solution, rather than acting independently.
- ✗
Escalate the issue to the Business Owners and request additional funding for a dedicated business analyst to write acceptance criteria.
Why it's wrong here
Escalating to Business Owners for funding is premature and does not follow the ART's improvement process. The Inspect and Adapt event is designed to identify and prioritize improvements, which are then added to the ART backlog. Requesting external resources bypasses the collaborative problem-solving approach and may not address the root cause effectively across teams.
About these practice questions
This SSM question is part of Courseiva's 385-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint
This SSM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the SSM exam.