SSM Supporting ART Events Practice Question
During the Inspect and Adapt event, the ART reviews metrics and identifies that the predictability measure has dropped from 90% to 70% over the last two PIs. The Scrum Master for Team Echo notices that the team consistently overcommits during PI Planning but meets its iteration goals. What is the most likely root cause the Scrum Master should help the team investigate during the Problem-Solving Workshop?
⚠ Common exam trap
The trap here is assuming that iteration success automatically translates to PI success, ignoring the different scope and commitment levels.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The team is committing to more PI Objectives than it can realistically deliver given its capacity and dependencies.
Predictability measures the percentage of PI Objectives met. When a team consistently meets iteration goals but misses PI Objectives, the problem is usually at the PI planning level: the team is committing to more than it can deliver. The Scrum Master should guide the team to examine its PI planning process, capacity allocation, and dependency management to align commitments with realistic delivery.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The team is committing to more PI Objectives than it can realistically deliver given its capacity and dependencies.
Why this is correct
If the team meets iteration goals but misses PI Objectives, the likely cause is overcommitment at the PI level. The team may be accepting too many features or underestimating dependencies and risks. The Scrum Master should facilitate a root-cause analysis on how PI Objectives are set and whether capacity and dependencies are accurately reflected during planning.
- ✗
The team is not conducting daily stand-ups effectively, leading to poor coordination.
Why it's wrong here
Ineffective stand-ups would typically affect iteration execution and goal completion. Since the team meets iteration goals, daily coordination is probably sufficient. The predictability drop is at the PI level, pointing to planning and commitment issues rather than daily execution.
- ✗
The team is not using the Program Board to track dependencies, causing integration delays.
Why it's wrong here
While dependency tracking is important, the symptom of meeting iteration goals but missing PI Objectives is more directly linked to overcommitment at the PI level. Integration delays would likely also impact iteration goals. The root cause is more likely in how PI Objectives are selected and sized.
- ✗
The team is not breaking down features into stories small enough to fit within an iteration.
Why it's wrong here
The team meets its iteration goals, so story sizing is likely adequate. The issue emerges at the PI level, where committed PI Objectives are not being met despite iteration success. This suggests a disconnect between iteration execution and PI planning commitments, not a story-sizing problem.
About these practice questions
One of 385 original SSM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint
This SSM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the SSM exam.