Courseiva
Supporting ART Events →hardMultiple Choice

SSM Supporting ART Events Practice Question

During the final plan review of PI Planning, the train is ROAMing risks. A team identifies a risk that they cannot resolve themselves, but the Release Train Engineer (RTE) takes ownership of it to find a solution later. How should this risk be categorized?

⚠ Common exam trap

Candidates often confuse 'Owned' with 'Resolved'. 'Owned' means we have a person responsible for it, but the risk itself still exists. 'Resolved' means the risk is no longer a concern.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Owned

The ROAM acronym stands for Resolved, Owned, Accepted, and Mitigated. When a risk is 'Owned,' it means that someone (in this case, the RTE) has taken responsibility for the risk because it cannot be resolved during the planning event. The owner will track the risk to ensure it is eventually addressed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Owned

    Why this is correct

    Owned risks are those that cannot be resolved during PI Planning. By assigning an owner, the ART ensures that the risk doesn't fall through the cracks. The owner is responsible for managing the risk and reporting back on its status during subsequent ART Sync or Coach Sync meetings.

  • ✗

    Accepted

    Why it's wrong here

    Accepted risks are those that the train simply acknowledges and chooses to live with, often because the cost of mitigation is higher than the potential impact. If the RTE is actively working to find a solution, the risk is not merely being accepted; it is being actively managed.

  • ✗

    Mitigated

    Why it's wrong here

    A risk is mitigated when a plan is developed to reduce its impact or probability. While the RTE taking ownership is a step toward mitigation, 'Mitigated' usually implies that a specific technical or process-based countermeasure has already been identified and incorporated into the team's or train's plan.

  • ✗

    Resolved

    Why it's wrong here

    A risk is only resolved if it is completely eliminated or no longer poses a threat to the PI. Simply having an owner does not make the risk go away; it just means there is a clear line of accountability for dealing with it as the Program Increment progresses.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

Courseiva writes every SSM question from scratch — 385 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This SSM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the SSM exam.