At the end of PI Planning, the confidence vote results in several '2-finger' votes. What is the Scrum Master's role in this situation?
⚠ Common exam trap
Candidates often mistakenly suggest ignoring low votes if the majority is high, or forcing the team to commit anyway, which undermines the core SAFe principle of building shared commitment.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Facilitate a discussion to address the concerns of those who voted low.
The confidence vote is a key ceremony that ensures everyone on the ART is committed to the plan. A low vote from any individual is not a failure but an opportunity to uncover hidden risks. The Scrum Master must ensure these voices are heard and that the plan is adjusted.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Ignore the low votes and proceed with the majority's decision.
Why it's wrong here
Ignoring low votes undermines the entire purpose of the confidence vote and creates a culture where risks are hidden rather than addressed. This approach leads to unrealistic plans and likely failure during the PI, as the concerns that led to the low vote will eventually manifest as real problems.
- ✓
Facilitate a discussion to address the concerns of those who voted low.
Why this is correct
Facilitating a discussion allows the person with the concern to explain their reasoning to the rest of the train and leadership. This often reveals a missing dependency or an unaddressed risk, allowing the ART to make the necessary adjustments to the plan and ultimately reach a higher level of confidence.
- ✗
Ask the Release Train Engineer to override the vote and move forward.
Why it's wrong here
Asking the RTE to override the vote is a violation of Agile principles and the self-organizing nature of ARTs. The vote represents the collective wisdom of the people doing the work, and forcing a commitment through authority will not resolve the underlying technical or logistical issues that caused the low confidence.
- ✗
Immediately start re-planning the entire PI for all teams.
Why it's wrong here
Re-planning the entire PI is usually a last resort and may not be necessary if the concerns are localized. The Scrum Master should first aim to address the specific issues raised by those who voted low, which might involve minor adjustments to a few team plans rather than a complete restart.
About these practice questions
This SSM question is part of Courseiva's 385-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint
This SSM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the SSM exam.