A team has finished all their assigned stories for the iteration early. What is the best course of action for the team to take?

⚠ Common exam trap

Candidates often choose 'start planning the next iteration' or 'take a break,' failing to recognize the SAFe principle of maximizing flow and value delivery within the current timebox.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Pull the next most important story from the team backlog.

High-performing teams should always look for ways to pull in additional work that provides value or improves the system. By proactively selecting the next most important item from the team backlog, the team optimizes their throughput and supports the overall goals of the Program Increment. This practice demonstrates an 'ownership' mindset and helps to maximize the value delivered within the timebox, which is a key goal of SAFe.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Start working on stories from the next iteration to get ahead.

    Why it's wrong here

    Working on future iterations can lead to premature implementation if requirements have not been fully refined or if priorities shift. It is better to focus on current, high-value tasks, technical debt reduction, or providing support to other teams on the Agile Release Train to ensure alignment and synchronization.

  • ✓

    Pull the next most important story from the team backlog.

    Why this is correct

    Pulling from the team backlog allows the team to deliver additional value within the existing iteration. This optimizes the team's capacity and keeps the focus on high-priority objectives. It is the most effective way to respond to the reality of finishing early while maintaining alignment with the product vision.

  • ✗

    Take the remainder of the iteration off to recover from the intense work.

    Why it's wrong here

    Taking time off during an active iteration is unproductive and violates the principle of flow. Even if stories are done, there are always opportunities for quality improvements, peer review, documentation, or technical debt reduction, which are all legitimate and valuable activities for a professional, high-performing development team.

  • ✗

    Conduct an unscheduled performance review for each team member.

    Why it's wrong here

    Performance reviews are not the team's responsibility and should not occur during the iteration. The team should focus on delivering value. If they find themselves with excess capacity, they should look at the backlog or help others, rather than engaging in administrative tasks that do not contribute to product.

About these practice questions

Courseiva writes every POPM question from scratch — 336 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.