A Product Owner notices that the team's Iteration Goals are consistently met, but the features delivered are not accepted by the System Demo because they do not meet the Definition of Done. The team insists they are completing all tasks in the iteration. What is the most likely root cause, and what should the Product Owner do?
⚠ Common exam trap
The trap here is assuming the problem is over-commitment or scope, when the real issue is often a misunderstood or ignored Definition of Done.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Definition of Done is not clear or not being followed; the Product Owner should facilitate a team discussion to refine and enforce it.
When iteration goals are met but features are rejected at the System Demo, the likely cause is a misaligned or ignored Definition of Done. The Product Owner must ensure the team understands and applies the DoD consistently, as it defines the quality bar for all increments. Clarifying the DoD and reinforcing it during refinement and iteration execution resolves the disconnect and prevents future rejections.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
The Definition of Done is not clear or not being followed; the Product Owner should facilitate a team discussion to refine and enforce it.
Why this is correct
The team is meeting iteration goals but failing system demo acceptance, indicating a mismatch between their understanding of Done and the actual quality criteria. The Product Owner should collaborate with the team to clarify and reinforce the Definition of Done, ensuring it is explicit and consistently applied to every increment.
- ✗
The System Demo is too rigorous; the Product Owner should work with the Release Train Engineer to relax acceptance criteria.
Why it's wrong here
Relaxing acceptance criteria undermines quality and does not solve the underlying problem. The System Demo is a critical inspect-and-adapt event, and its criteria are based on the Definition of Done. Instead of weakening standards, the PO should help the team meet them.
- ✗
The team is over-committing; the Product Owner should reduce the number of stories in the next iteration.
Why it's wrong here
Over-commitment typically results in missed goals, but here goals are met. The issue is quality, not quantity. Reducing stories may temporarily mask the problem but will not fix the unclear Definition of Done. The PO must address the quality gap directly.
- ✗
The team is not including non-functional requirements in their tasks; the Product Owner should add them to the Team Backlog.
Why it's wrong here
While non-functional requirements are important, they are typically part of the Definition of Done and should already be included. Adding them as separate backlog items does not address the core issue of the team's misunderstanding of Done. The PO should first ensure the DoD is clear and followed, rather than adding more work.
Visual reference
About these practice questions
This POPM question is part of Courseiva's 336-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint
This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.