PI Execution →hardMultiple Choice

POPM PI Execution Practice Question

A Product Manager is reviewing the ART's progress at the end of Iteration 3. The team has completed all committed features, but the System Demo revealed that the integrated solution does not meet the expected nonfunctional requirements for performance. The teams are confident they can fix the issues in the next iteration, but this will delay a key PI Objective. What should the Product Manager do first?

⚠ Common exam trap

The trap here is assuming that performance issues can be deferred to a hardening iteration or next PI, rather than addressing them as soon as they are identified.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Collaborate with the teams to prioritize the performance fixes in the team backlog for the next iteration, and assess the impact on the PI Objective with the Release Train Engineer.

The Product Manager should immediately prioritize the performance fixes in the team backlog and collaborate with the Release Train Engineer to assess the impact on the PI Objective. This ensures that the ART addresses the quality gap while maintaining transparency. Deferring or canceling the objective without attempting a resolution would be premature and could harm stakeholder trust.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Direct the teams to continue with the planned features for the next iteration and address performance issues in a hardening iteration at the end of the PI.

    Why it's wrong here

    Deferring performance fixes to a hardening iteration contradicts SAFe's principle of continuous value delivery and built-in quality. It risks accumulating technical debt and may lead to a last-minute crisis. The Product Manager should prioritize fixes as soon as they are discovered to maintain system integrity.

  • ✗

    Escalate the performance issues to the Business Owners and recommend canceling the PI Objective to avoid further investment.

    Why it's wrong here

    Canceling the PI Objective is an extreme reaction that may not be warranted. The Product Manager should first explore options to remediate the performance issues. Escalation without a proposed solution can undermine confidence and does not demonstrate the proactive problem-solving expected of a Product Manager.

  • ✓

    Collaborate with the teams to prioritize the performance fixes in the team backlog for the next iteration, and assess the impact on the PI Objective with the Release Train Engineer.

    Why this is correct

    This action directly addresses the problem by prioritizing the necessary fixes and evaluating the effect on the PI Objective. The Product Manager works with teams to adjust the backlog and with the RTE to understand cross-team implications, ensuring the ART can still meet its commitments or transparently adjust them.

  • ✗

    Accept the demo results and work with the teams to renegotiate the PI Objective with stakeholders, adjusting scope to include performance fixes in the next PI.

    Why it's wrong here

    Renegotiating the PI Objective at this point may be premature. The Product Manager should first assess whether the performance issues can be resolved within the current PI. Deferring to the next PI could erode stakeholder trust and delay value delivery, especially if the fix is feasible in the remaining iterations.

About these practice questions

This POPM question is part of Courseiva's 336-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.