PI Planning Preparation →easyMultiple Choice

POPM PI Planning Preparation Practice Question

A Product Manager is preparing for PI Planning and needs to ensure that the Program Backlog is prioritized effectively. Which artifact should the PM primarily use to sequence features for the upcoming PI?

⚠ Common exam trap

Candidates often confuse the Program Board or PI Objectives with the backlog used for prioritization; the Program Backlog is the correct artifact.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

The Program Backlog

The Program Backlog is the PM's primary tool for prioritizing features before PI Planning. By applying WSJF, the PM sequences features based on economic value and job size. This prioritized backlog is then presented to the ART during PI Planning, enabling teams to plan the most valuable work first and align with business goals.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The PI Objectives

    Why it's wrong here

    PI Objectives are the outcomes that teams commit to during PI Planning. They are created after the backlog is prioritized and are not used to sequence features beforehand. The PM may draft PI Objectives, but they are not the primary artifact for prioritization.

  • ✗

    The Team Backlog

    Why it's wrong here

    The Team Backlog is owned by the Product Owner and contains user stories for a single team. It is not used by the PM to prioritize features across the ART. The PM focuses on the Program Backlog, which aggregates features from multiple teams and is the basis for PI Planning.

  • ✗

    The Program Board

    Why it's wrong here

    The Program Board is a visual tool used during PI Planning to show dependencies and milestones. It is not used to prioritize the Program Backlog before the event. The PM uses the Program Board during planning to facilitate coordination, but prioritization of features occurs beforehand using the Program Backlog and WSJF.

  • ✓

    The Program Backlog

    Why this is correct

    The Program Backlog is the primary artifact for the PM to prioritize features before PI Planning. It contains the features that the ART will work on, and the PM applies WSJF to sequence them. This prioritized backlog is then used as input for PI Planning, ensuring that teams plan the highest-value work first.

About these practice questions

One of 336 original POPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint

This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.