POPM PI Planning Preparation Practice Question
A Product Manager is preparing for an upcoming PI Planning event. The ART's current PI Objectives are not achieving the expected business outcomes, and capacity data shows significant unused potential. The PM wants to ensure the next PI Planning is more effective. Which action best prepares the PM for PI Planning?
⚠ Common exam trap
The trap here is thinking that adding more capacity or demos can fix misalignment, when the real issue is often an outdated or poorly prioritized Program Backlog and Vision.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Conduct a market and customer analysis to update the ART's Vision and refine the Program Backlog with prioritized features before the event.
The correct answer emphasizes the PM's responsibility to own the Vision and Program Backlog. Before PI Planning, the PM should analyze market and customer needs to ensure the backlog reflects the highest-value work. This preparation directly enables teams to create meaningful PI Objectives that drive business outcomes, addressing the gap between current objectives and expected results.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Delegate the preparation of PI Objectives to the Scrum Masters and focus on facilitating the PI Planning event itself.
Why it's wrong here
PI Objectives are developed by teams during PI Planning, but the PM must prepare by ensuring the Program Backlog is prioritized and the Vision is communicated. Delegating preparation to Scrum Masters abdicates the PM's core responsibility. The PM's involvement in shaping the Vision and backlog is critical for a successful event.
- ✗
Ask the Release Train Engineer to increase the number of teams on the ART to improve capacity utilization.
Why it's wrong here
Adding teams does not address the underlying problem of misaligned objectives. Capacity utilization is a symptom, not the cause. The PM's role in preparation is to ensure the right work is in the backlog and the Vision is clear. Increasing team count without addressing alignment would likely worsen coordination and reduce effectiveness.
- ✓
Conduct a market and customer analysis to update the ART's Vision and refine the Program Backlog with prioritized features before the event.
Why this is correct
This is correct because PI Planning success depends on a clear, current Vision and a well-prioritized Program Backlog. By analyzing market and customer needs, the PM ensures the ART is planning against the most valuable work. This directly addresses the gap between current objectives and expected outcomes, and aligns with SAFe guidance that the PM owns the Vision and Program Backlog.
- ✗
Schedule additional system demos during the PI to showcase progress and gather feedback from stakeholders.
Why it's wrong here
While system demos are valuable, scheduling more demos does not prepare the PM for PI Planning. The issue is that current objectives are not achieving outcomes; adding demos addresses feedback frequency, not the root cause of misalignment. This action is more appropriate during execution, not as a preparation step before PI Planning.
About these practice questions
One of 336 original POPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official Scaled Agile exam blueprint
This POPM practice question is part of Courseiva's free Scaled Agile certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the POPM exam.