Refer to the exhibit. What action does the LPM team need to take to align with the policy?
Exhibit
LPM Policy: - Enabler Epics: 20% of capacity - Business Epics: 80% of capacity Scenario: The team has 10,000 hours of capacity. Currently, 3,000 hours are allocated to Enablers.
Trap 1: Increase the business epic capacity to 12,000 hours.
Increasing the total capacity to 12,000 hours to make the existing 3,000 hours of Enabler work equal 25% does not solve the underlying issue of exceeding the 20% guardrail. The guardrail represents a percentage-based balance, and simply inflating the total capacity is a mathematical loophole, not a strategic adjustment.
Trap 2: Ignore the policy because Enabler work is critical for long-term…
Ignoring established investment guardrails undermines the governance model of Lean Portfolio Management. While Enabler work is vital, it must exist within the constraints agreed upon by the stakeholders. If the policy is consistently wrong, the correct action is to formally negotiate a change, not to unilaterally ignore it.
Trap 3: Apply for an exception from the Portfolio Steering Committee to…
An exception should only be requested if there is a compelling, time-sensitive reason to violate the policy. Before escalating for an exception, the team should attempt to balance the portfolio themselves. Excessive escalation for every minor policy misalignment creates bureaucracy and demonstrates a lack of operational discipline and maturity.
- A
Increase the business epic capacity to 12,000 hours.
Why it fails: Increasing the total capacity to 12,000 hours to make the existing 3,000 hours of Enabler work equal 25% does not solve the underlying issue of exceeding the 20% guardrail. The guardrail represents a percentage-based balance, and simply inflating the total capacity is a mathematical loophole, not a strategic adjustment.
- B
Shift 1,000 hours from Enabler work to Business Epics.
To meet the 20% policy limit (2,000 hours), the team must reduce their current 3,000-hour commitment to Enablers by 1,000 hours. Moving those hours to Business Epics restores the intended strategic balance defined by the investment guardrails, ensuring the portfolio is prioritizing the delivery of customer-facing features as planned.
- C
Ignore the policy because Enabler work is critical for long-term system stability.
Why it fails: Ignoring established investment guardrails undermines the governance model of Lean Portfolio Management. While Enabler work is vital, it must exist within the constraints agreed upon by the stakeholders. If the policy is consistently wrong, the correct action is to formally negotiate a change, not to unilaterally ignore it.
- D
Apply for an exception from the Portfolio Steering Committee to increase Enabler capacity.
Why it fails: An exception should only be requested if there is a compelling, time-sensitive reason to violate the policy. Before escalating for an exception, the team should attempt to balance the portfolio themselves. Excessive escalation for every minor policy misalignment creates bureaucracy and demonstrates a lack of operational discipline and maturity.