Universal Containers is preparing for a major Sales Cloud go-live. Which TWO activities are critical components of the cutover plan? (Choose two.)
Delta loads capture records created or modified since the initial migration, and validation checks confirm record counts, field integrity and relationship accuracy before users gain access. This satisfies the cutover plan's requirement to synchronise source and target systems at the go-live moment, preventing data loss or duplication.
Why this answer
Option B is correct because a cutover plan must include the final data migration delta loads and validation checks to ensure that any records created or changed since the last full load are brought into production and verified before users go live. Option E is correct because smoke testing in production validates that core integrations, profiles, and critical business processes function correctly in the live environment immediately after cutover. Option A is not part of cutover, since requirements gathering belongs to the earlier discovery and design phases.
Option C is not a cutover activity, as licensing is handled during contracting and procurement. Option D is incorrect because managed packages are typically installed or deployed as part of the release, not uninstalled during cutover.
Exam trap
Sales-Con-201 often tests the boundary between cutover activities and earlier project phases (requirements, procurement), tempting candidates to select initiation or contracting tasks as cutover components.