You notice that the 'Residual Risk' is higher than the 'Inherent Risk' after mitigation. What does this suggest?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The mitigation strategy may have introduced secondary risks
If residual risk is higher, the mitigation strategy may be introducing new threats or failing to address the primary risk.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The risk is now fully accepted
Why it's wrong here
Acceptance does not change the risk values.
- ✗
The mitigation was highly successful
Why it's wrong here
Successful mitigation lowers residual risk.
- ✓
The mitigation strategy may have introduced secondary risks
Why this is correct
A common sign of a failed or counterproductive mitigation strategy.
- ✗
The project is complete
Why it's wrong here
Residual risk is relevant until project closure.
About these practice questions
One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.