When utilizing a tornado diagram in Oracle Primavera Risk Analysis to conduct sensitivity analysis, which metric indicates the highest impact on the project finish date?
Trap 1: The activity with the highest 'Float' value.
High float usually indicates lower impact on the critical path.
Trap 2: The activity with the lowest baseline duration.
Duration length does not necessarily correlate with risk impact.
Trap 3: The activity with the most resource assignments.
Number of resources is not the primary driver for sensitivity in a tornado diagram.
- A
The activity with the largest positive correlation coefficient.
The correlation coefficient represents the strength of the relationship between the activity and project completion.
- B
The activity with the highest 'Float' value.
Why it fails: High float usually indicates lower impact on the critical path.
- C
The activity with the lowest baseline duration.
Why it fails: Duration length does not necessarily correlate with risk impact.
- D
The activity with the most resource assignments.
Why it fails: Number of resources is not the primary driver for sensitivity in a tornado diagram.