PMI-RMP Risk Monitoring And Reporting Practice Question
Which TWO stakeholders are most likely to request a detailed 'Risk Report'?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The project sponsor
The project sponsor and project manager need high-level and detailed risk insights respectively.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The office receptionist
Why it's wrong here
Not a project stakeholder for risk reporting.
- ✗
The local newspaper reporter
Why it's wrong here
External press is not a routine report recipient.
- ✓
The project sponsor
Why this is correct
Sponsors are accountable and need visibility on major risks.
- ✓
The project manager
Why this is correct
The project manager is responsible for the day-to-day risk management.
- ✗
The catering service staff
Why it's wrong here
Not a project stakeholder for risk reporting.
About these practice questions
This PMI-RMP question is part of Courseiva's 200-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.