Which TWO of the following are prerequisites for conducting a valid Monte Carlo simulation in a project schedule?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Probability distributions for task durations.
A well-defined network logic and accurate, probabilistic duration estimates are essential foundations for any reliable simulation.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Probability distributions for task durations.
Why this is correct
Distributions are needed for the random sampling process.
- ✗
Hardware specifications for the simulation server.
Why it's wrong here
Hardware is a secondary operational concern, not a project requirement.
- ✗
A finalized project charter.
Why it's wrong here
The charter is useful but not a technical requirement for the simulation software.
- ✓
A complete and logically linked network diagram.
Why this is correct
Logic is required for the simulation to propagate effects.
- ✗
A list of all project stakeholders.
Why it's wrong here
Stakeholder lists are not required for quantitative risk simulation.
About these practice questions
This PMI-RMP question is part of Courseiva's 200-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.