PMI-RMP Stakeholder Engagement Practice Question
Which THREE outcomes are expected from an effective stakeholder engagement plan for risk management?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Increased accuracy in risk identification through diverse stakeholder input.
Effective engagement results in better risk identification, ownership, and overall project performance.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Increased accuracy in risk identification through diverse stakeholder input.
Why this is correct
Diverse input leads to better quality data.
- ✗
A significant reduction in project scope.
Why it's wrong here
Risk management is not about changing scope.
- ✗
A total elimination of all project risks.
Why it's wrong here
Elimination is rarely possible; management is the goal.
- ✓
Improved ownership of risk responses by those best positioned to execute them.
Why this is correct
Involvement fosters accountability.
- ✓
Enhanced alignment between risk management activities and project goals.
Why this is correct
Engagement ensures that risk management supports the project's success.
About these practice questions
One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.