PMI-RMP Specialized Risk Analyses Practice Question
Which THREE of the following are common pitfalls when performing an Expected Monetary Value (EMV) analysis?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Failing to account for the impact of the risks on subsequent tasks.
Overly optimistic probabilities, ignoring secondary risks, and failing to account for the impact of risks on project dependencies are all common errors.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Failing to account for the impact of the risks on subsequent tasks.
Why this is correct
Dependencies propagate risk throughout the project.
- ✓
Using overly optimistic probability estimates.
Why this is correct
Subjectivity often leads to under-estimating risks.
- ✓
Ignoring the correlation between different risk events.
Why this is correct
Risks rarely happen in isolation.
- ✗
Performing the analysis before the project starts.
Why it's wrong here
Pre-project analysis is a best practice.
- ✗
Using a currency that is too stable.
Why it's wrong here
Currency stability is not a pitfall of EMV calculation.
About these practice questions
This PMI-RMP question is part of Courseiva's 200-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.