Which THREE data inputs are required to model a risk event in a quantitative simulation?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Impact (duration or cost) if the risk occurs.
To define a risk, you need to know if/how it happens (probability), how much it costs or delays (impact), and which specific tasks it affects (scope/linkage).
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Impact (duration or cost) if the risk occurs.
Why this is correct
Impact defines the magnitude of the risk.
- ✗
The current market inflation rate.
Why it's wrong here
Inflation is usually handled outside of specific risk event modeling.
- ✗
The risk owner's contact information.
Why it's wrong here
This is administrative, not modeling data.
- ✓
Task linkage or scope of impact.
Why this is correct
You must define which parts of the project are affected.
- ✓
Probability of occurrence.
Why this is correct
Probability is essential for triggering the event.
About these practice questions
One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.