Courseiva
Risk Process FacilitationeasyMultiple ChoiceObjective-mapped

PMI-RMP Risk Process Facilitation Practice Question

Which of the following is NOT a common risk identification technique?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk response planning

Risk response planning is a process step, not an identification technique.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • SWOT analysis

    Why it's wrong here

    This is a common identification technique.

  • Brainstorming

    Why it's wrong here

    This is a common identification technique.

  • Risk response planning

    Why this is correct

    This is a separate process, not a technique for identifying risks.

  • Checklist analysis

    Why it's wrong here

    This is a common identification technique.

About these practice questions

One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.