Courseiva
Stakeholder EngagementeasyMultiple ChoiceObjective-mapped

PMI-RMP Stakeholder Engagement Practice Question

Which document outlines how risk management activities will be communicated to stakeholders?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Communications Management Plan.

The Communications Management Plan defines the 'who, what, when, and how' of project communication.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Project Charter.

    Why it's wrong here

    The charter is a high-level authorization document.

  • The Risk Register.

    Why it's wrong here

    The register lists risks, not the communication plan.

  • The Communications Management Plan.

    Why this is correct

    This plan explicitly defines communication protocols.

  • The Resource Management Plan.

    Why it's wrong here

    This plan focuses on team and equipment allocation.

About these practice questions

Courseiva writes every PMI-RMP question from scratch — 200 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.