PMI-RMP Stakeholder Engagement Practice Question
Which document outlines how risk management activities will be communicated to stakeholders?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Communications Management Plan.
The Communications Management Plan defines the 'who, what, when, and how' of project communication.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Project Charter.
Why it's wrong here
The charter is a high-level authorization document.
- ✗
The Risk Register.
Why it's wrong here
The register lists risks, not the communication plan.
- ✓
The Communications Management Plan.
Why this is correct
This plan explicitly defines communication protocols.
- ✗
The Resource Management Plan.
Why it's wrong here
This plan focuses on team and equipment allocation.
About these practice questions
Courseiva writes every PMI-RMP question from scratch — 200 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.