Courseiva
Specialized Risk AnalyseseasyMultiple ChoiceObjective-mapped

PMI-RMP Specialized Risk Analyses Practice Question

Which document is the primary input for identifying risks to be included in a quantitative risk analysis?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Risk Register.

The Risk Register, developed during the Qualitative Risk Analysis phase, identifies the risks that are prioritized for further quantitative study.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk Register.

    Why this is correct

    The Risk Register contains the identified risks required for analysis.

  • Stakeholder Engagement Plan.

    Why it's wrong here

    This focuses on communication, not risk data.

  • Lessons Learned Repository.

    Why it's wrong here

    Useful for identification, but the Risk Register is the formal input.

  • Project Charter.

    Why it's wrong here

    The Charter is too high-level for specific risk quantification.

About these practice questions

One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.