When facilitating a risk workshop, how do you handle a suggestion that is clearly out of scope for the current project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Acknowledge the input and record it in the 'Parking Lot' for future consideration

Address the suggestion respectfully and document it as a potential item for future consideration or outside the project's current bounds.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Include it in the risk register anyway

    Why it's wrong here

    This clutters the register with invalid risks.

  • Ask the stakeholder to leave

    Why it's wrong here

    This is inappropriate facilitation.

  • Acknowledge the input and record it in the 'Parking Lot' for future consideration

    Why this is correct

    The 'Parking Lot' is a standard facilitation tool for off-topic but important ideas.

  • Immediately dismiss it

    Why it's wrong here

    Dismissing input discourages stakeholders.

About these practice questions

This PMI-RMP question is part of Courseiva's 200-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.