PMI-RMP Specialized Risk Analyses Practice Question
What is the primary output of a sensitivity analysis in a project risk assessment?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Identification of the most influential project variables.
Sensitivity analysis identifies which variables have the most significant impact on project objectives, allowing teams to focus on critical risks.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
A total project cost estimate.
Why it's wrong here
Cost estimation is a different process.
- ✗
A project management plan.
Why it's wrong here
Sensitivity analysis is a tool for the plan, not the plan itself.
- ✓
Identification of the most influential project variables.
Why this is correct
The core goal is identifying what matters most.
- ✗
A list of all possible project risks.
Why it's wrong here
This is the risk register.
About these practice questions
Courseiva writes every PMI-RMP question from scratch — 200 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed August 2026 · checked against the official PMI exam blueprint
This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.