PMI-RMP Specialized Risk Analyses Practice Question

What is the primary output of a sensitivity analysis in a project risk assessment?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Identification of the most influential project variables.

Sensitivity analysis identifies which variables have the most significant impact on project objectives, allowing teams to focus on critical risks.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • A total project cost estimate.

    Why it's wrong here

    Cost estimation is a different process.

  • A project management plan.

    Why it's wrong here

    Sensitivity analysis is a tool for the plan, not the plan itself.

  • Identification of the most influential project variables.

    Why this is correct

    The core goal is identifying what matters most.

  • A list of all possible project risks.

    Why it's wrong here

    This is the risk register.

About these practice questions

Courseiva writes every PMI-RMP question from scratch — 200 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.