Courseiva
Risk Monitoring And ReportinghardMultiple ChoiceObjective-mapped

PMI-RMP Risk Monitoring And Reporting Practice Question

During a risk review, a stakeholder asks why a risk's impact has not changed despite a completed mitigation plan. What is the most likely cause?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The mitigation addressed probability, not impact

If the risk is an 'inherent' risk, mitigation might reduce probability but not the theoretical impact, or the plan was ineffective.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project manager forgot to save the update

    Why it's wrong here

    While possible, it is not a project management principle-based explanation.

  • The mitigation addressed probability, not impact

    Why this is correct

    Mitigation plans often target either the likelihood or the consequence; if impact remains high, the plan likely targeted probability.

  • The risk is a secondary risk

    Why it's wrong here

    This does not explain why the impact assessment remained static.

  • The risk register is corrupted

    Why it's wrong here

    Corruption is an unlikely reason for static data.

About these practice questions

One of 200 original PMI-RMP practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed August 2026 · checked against the official PMI exam blueprint

This PMI-RMP practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PMI-RMP exam.